In a statment released on Wednesday, the Nelson Mandela Bay Municipality said residents were hereby notified that the City requires a 48-hour shutdown of the Chelsea reservoir in order to perform the final connection for the new KwaNobuhle Pump Station.
The shutdown is scheduled for Tuesday, April 12, 2022, however, teams will start isolating and draining the system on April 11, 2022.
This will allow the contractor on site to connect the suction pipeline for the new KwaNobuhle pump station to the 750mm pipeline of the Chelsea reservoir.
To safely complete the above-mentioned mentioned work, the Chelsea reservoir must be emptied.
While we have made every effort to ensure that water is maintained in the majority of areas, we anticipate that some areas may experience water disruptions during this time.
Water pressure may be low or non-existent in the following areas:
1.Rowallan Park
2.Francis Evatt Park
3.Hunters Retreat
4.Bay West
5.Parsonsvlei / Westbrook
6.Morningside
7.Kabega Park
8.Sherwood
9.Westering
10.Cotswold
11.Helenvale
12.Malabar
13.Parts of Schauderville
14.Framesby
15.Sunridge Park
16.Parts of Lorraine
17.Parts of Theescombe
18.Kamma Park
If necessary, water tankers will be dispatched, and their locations will be communicated via social media. Additional information can be obtained by calling the Service Delivery Call Centre at 0800 20 50 50.
NELSON MANDELA BAY | MUNICIPALITY WARNS OF 48 HOUR WATER SHUTDOWN OF THE CHELSEA RESERVOIR